PMP考试考题一:

The project sponsor is concerned about several defects being reported during the quality control phase and asks the project manager to investigate the source for these defects. That tool should the project manager use to perform this task?

A.Control chart

B.Pareto chart

C.Fishbone diagram

D.inspection

项目出资人担忧在质量管理环节中汇报的好几个缺点,规定项目主管调研这种缺点的缘故。项目主管应当应用哪些专用工具来实行此项每日任务?

A.控制图

B.帕累托图

C.鱼骨图

D.监测

PMP参考答案分析:调研缺点缘故用鱼骨图。

PMP答案:C

PMP考试考题二

During project closure, the project manager records information in the company’s inventory for future project knowledge. The project manager works on which of the following assets?

A.Approved change requests

B.Quantitative risk analysis

C.Accepted deliverables

D.Historical information

在项目结束期内,项目主管升级了企业的资料库,运用于将来项目。项目主管正从业以下哪一财产工作中?

A.已准许的变动恳求

B.定量分析风险评估

C.已接纳的可交货成效

D.历史时间信息内容

PMP参考答案分析:PMBOK原句:把历史时间信息内容和成功经验信息内容存进成功经验知识库系统,供将来项目或环节应用。可包含难题与风险性的信息内容,及其适用将来项目的合理技术性的信息内容。

PMP答案:D