pmp培训练习题209

pmp培训练习题209


在项目实行期内,一名精英团队组员常常埋怨说沒有立即出示一些信息内容。项目主管应当如何做?

A.查验该精英团队组员业绩考核历史纪录 

B.与全部精英团队组员按时举办情况通报会 

C.与该精英团队组员举办一对一的大会 

D.核查沟通交流管理方案


参考答案:D


此题在考第10章沟通交流管理,监管沟通交流全过程。信息的传递出現难题,一般 最先要做的就是说核查沟通交流管理方案,看方案是不是存在的问题是不是必须调节。


During the implementation of the project, an elite team member often complained that he did not show some information immediately. What should project managers do?


A. check the performance appraisal history of the elite team members


B. hold briefing with all elite team members on time


C. one to one meeting with the elite team members


D. verification, communication and exchange management plan


Reference answer: D


This question is in Chapter 10 communication management, supervision and communication process. When there is a problem in the transmission of information, generally the first thing to do is to check the communication and exchange management plan to see if there is a problem in the plan and whether it must be adjusted.